🌍 CASE STUDY · NIGERIA

Case Study: 15,000 BPH Detergent Line in Lagos, Nigeria

📅 June 5, 2026 · ⏱️ 10 min read · ✍️ CHANFER Projects Team

A West African FMCG manufacturer increased production capacity by 320%, reduced per-unit packaging cost by 28%, and achieved 99.2% OEE within 6 months of commissioning a CHANFER turnkey line.

The Client Challenge

Our client, a Lagos-based detergent manufacturer founded in 2018, had grown to 4,500 BPH using semi-automatic equipment imported from India. By early 2025, they faced a critical bottleneck:

The CHANFER Solution

After a 3-month evaluation comparing 6 vendors from China, India, and Germany, the client selected CHANFER for the turnkey project. The scope included:

Equipment Package

Service Package

Implementation Timeline

Phase Duration Key activities
Order & engineering 6 weeks Contract signing, 30% deposit, engineering design approval
Manufacturing 10 weeks Component fabrication, assembly, factory testing, FAT report
Shipping & clearance 5 weeks FCL shipment Lagos, customs clearance, inland transport
Installation 4 weeks Mechanical install, electrical wiring, utility connections, SAT
Training & ramp-up 2 weeks Operator training, production trials, performance optimization
Total project 27 weeks From order to full production

Results After 6 Months

+320%
Production capacity (4,500 → 15,000 BPH)
-28%
Per-unit packaging cost
99.2%
OEE (vs. 78% on old line)
18→6
Operators per shift

Quality Improvements

Financial Impact

Client Testimonial

"We evaluated packaging line suppliers from 6 countries. CHANFER won not just on price, but on the strength of their engineering team and after-sales support plan. The on-site installation was flawless, and their Lagos-based service engineer has been responsive within hours, not days. We've since ordered a second line for our pouch operation."
— Production Director, Lagos Detergent Manufacturer

Lessons Learned

For buyers considering similar projects in Africa, three insights stand out:

  1. Local service capability matters more than equipment price. A $20K savings on a Chinese line becomes a $200K loss if you can't get spare parts or engineers quickly.
  2. Plan utilities carefully. Many African facilities have unstable power—budget for voltage stabilizers, backup generators, and surge protection.
  3. Multi-format capability pays back fastest. Lines that can switch between bottle sizes recover the investment 30% faster than single-format lines.

Planning a Similar Project?

Get a custom feasibility study and ROI projection for your specific market and production requirements.

Request Feasibility Study →

Related Resources